CONSTRUCTION & TRAFFIC DELAYS
Yosemite Valley Parking and Road Construction
Contractors are wrapping up work for their winter shutdown. The only work that will take place this winter will be reconstructing masonry headwalls, with local traffic control as needed. Masonry contractors have wrapped up work in west Yosemite Valley and moved to the Lodge area. (L. Acree)
_______________________
Yosemite Valley Building Demolition
The abatement and demolition of the AAC Center began on Monday, November 6th and will continue through November 22nd, with the building demolition phase scheduled November 27th – December 18th. The accessible pedestrian pathway from the new Yosemite Village Day Use Parking Area to Yosemite Village (to the Village Store, Visitors Center, etc.) will not be blocked and will have chain link fencing on the interior side for visitor protection. The site will be restored to a seasonal wetland in 2018. (D. Miller)